Write your project charter.
Seven steps from a vague annoyance to a one-page charter your sponsor can say yes to: problem, scope, goal, metric, team, timeline and risks. With a worked example and a template.
What is inside.
- Seven steps, each with a good and a weak example
- A fully worked sample charter
- A fill-in template you can download as a text file
- Common mistakes to avoid
Demo shop: test payments only, no real money moves. After buying, find the guide under My purchases.
The seven steps.
1. Problem statement
Say what is wrong, where, how big and since when, with a number. No cause and no solution in it.
Weak: “Our invoicing is slow.” Better: “In the last three months, 22% of invoices were sent more than five days after delivery.”
2. Scope
Name where the project starts and ends in the process, and list what is out. A tight scope finishes; a loose one drifts.
Example: in scope, from delivery confirmation to invoice sent; out of scope, payment collection.
3. Goal
One measurable target with a date. Use the same measure as the problem statement.
Example: reduce late invoices from 22% to under 5% by the end of the sixth month.
4. Metric
Define exactly how you count: the unit, the formula, the data source and who measures. Agree on this before you start measuring.
Example: late invoice = sent more than five working days after delivery confirmation, counted weekly from the billing system.
5. Team and roles
Name the sponsor, the project leader and two to five members who know the process. Say how much time each gives.
6. Timeline
Give a date for each DMAIC phase: Define, Measure, Analyse, Improve, Control. Leave room for the control phase; it is the one that gets squeezed.
7. Risks and assumptions
List what could stop the project (people on leave, data you cannot get, a system change) and what you are assuming. Add who handles each.
Mistakes to avoid
Hiding a solution inside the problem statement (“we need a new system”).
A goal with no number or no date.
A scope that covers the whole company.
A worked example.
Sample only: a made-up company and made-up numbers.
- Project
- Faster invoicing at Northfield Supplies (sample)
- Problem statement
- In the last three months, 22% of invoices were sent more than five working days after delivery confirmation, which delays payment.
- Scope
- In: delivery confirmation to invoice sent, all standard orders. Out: payment collection, special contracts.
- Goal
- Reduce late invoices from 22% to under 5% within six months.
- Metric
- Share of invoices sent more than five working days after delivery confirmation, counted weekly from the billing system.
- Team
- Sponsor: finance manager. Leader: billing team lead. Members: two billing clerks, one warehouse coordinator, one analyst (about four hours a week each).
- Timeline
- Define: weeks 1 to 2. Measure: weeks 3 to 6. Analyse: weeks 7 to 10. Improve: weeks 11 to 18. Control: weeks 19 to 26.
- Risks and assumptions
- Quarter-end peak may hide the improvement (compare like with like). Billing data needs a weekly export from IT. Assumes the warehouse confirms deliveries the same day.